Any "Latest & Greatest" about Endeavor?
#2101
Gets Weekends Off
Joined APC: Oct 2015
Position: Inverted
Posts: 402
Somebody in OKC get paid by the hour doing approvals!
Sent from my iPhone using Tapatalk
#2102
Banned
Joined APC: Sep 2015
Posts: 519
Since Jepps is shutting down the offset presses, keeping paper subscriptions will become too costly to be effective. Surprised Endeavor hasn't realized this yet.
Jepp Stops the Presses | EAA AirVenture
Jepp Stops the Presses | EAA AirVenture
#2103
Because that's not how the FAA works. It may be faster to get something that has already approved elsewhere approved for us, but they still have to give us the blessing. Manuals have to be written. Training programs developed, backup plans made, etc etc. It's not as simple as just handing everyone an iPad.
#2104
EFBs will be online by the end of the year. They are going to start the testing phase soon. Right now they are looking at platforms and mounts. This is what we were told by the fleet manager in recurrent this week. He is on the planning committee for EFBs. Also our VP of flight ops has gotten the budget through to the finance department.
#2105
Gets Weekends Off
Joined APC: Jul 2008
Posts: 787
Since Jepps is shutting down the offset presses, keeping paper subscriptions will become too costly to be effective. Surprised Endeavor hasn't realized this yet.
Jepp Stops the Presses | EAA AirVenture
Jepp Stops the Presses | EAA AirVenture
I agree though, we look like fools hauling around flight cases.
#2106
Line Holder
Joined APC: Apr 2014
Posts: 33
My understanding is that its the entire approval process that takes the 12 months.
Not the first phase. we'll see the testing on the line from select pilots within 6 months, and like the poster above said, full implementation by the end of 2016.
Looking forward to never worrying about Jepp updates again. This was long overdue, but at least happening.
Sent from my iPhone using Tapatalk
Not the first phase. we'll see the testing on the line from select pilots within 6 months, and like the poster above said, full implementation by the end of 2016.
Looking forward to never worrying about Jepp updates again. This was long overdue, but at least happening.
Sent from my iPhone using Tapatalk
#2107
Even after they're issued, enjoy hauling BOTH around for a while. We've had the Surface 3 here at XE for 3 months now, still have to lug the 40-pound OJI-maker around and keep it all up to date. Apparently some people here still don't understand that you have to keep everything, both paper and electronic, up to date and fully charged when you start your day before the FAA will give us the blessing to have our big Jepp bonfire.
#2109
#2110
Gets Weekends Off
Joined APC: May 2015
Position: LAV
Posts: 187
In an email dated 12/23/15, the following information was given. Phase I is already in motion and phase III is said to be complete by the second quarter of 2016
Phase I - Month 1
Initial written notification to and formal planning meeting with FAA.
Phase II - Months 2&3
Application
· Hardware and application specifics (off shelf)
· Manual revisions
· Procedures checklist
· Training Program (LMS) (off-shelf)
· EFB evaluation report
· Rapid Decompression Report (off shelf)
· Non-interference tests (Fleet Manager)
Phase III - Month 4 & 5
PI review including simulator or flight evaluation
Phase IV - (validation) - Months 6-11
Temporary AO61 issued for 6 month validation period. During this time devices noted in application may be utilized provided all current materials are carried (paper manuals, charts, etc.)
Phase V - (paperless flight deck) - Month 12
Authorization to use EFB ~ A061
Phase VI - TBD
Present business case for Company sponsored devices to Delta Finance.
Phase I - Month 1
Initial written notification to and formal planning meeting with FAA.
Phase II - Months 2&3
Application
· Hardware and application specifics (off shelf)
· Manual revisions
· Procedures checklist
· Training Program (LMS) (off-shelf)
· EFB evaluation report
· Rapid Decompression Report (off shelf)
· Non-interference tests (Fleet Manager)
Phase III - Month 4 & 5
PI review including simulator or flight evaluation
Phase IV - (validation) - Months 6-11
Temporary AO61 issued for 6 month validation period. During this time devices noted in application may be utilized provided all current materials are carried (paper manuals, charts, etc.)
Phase V - (paperless flight deck) - Month 12
Authorization to use EFB ~ A061
Phase VI - TBD
Present business case for Company sponsored devices to Delta Finance.